Troon Progress Update April 2026
Site Progress So Far
Transforming the Existing Building
Significant early works have now been completed, laying the foundations for the new facility:
• Internal strip-out works fully completed
• Removal of outdated infrastructure in changing areas
• Drainage systems installed below ground
• Structural supports added for existing plant equipment
Building the Foundations for New Spaces
Work is well underway on the new extension areas and structural base:
• Ground beams and pile caps installed
• Formation works progressing in new activity spaces
• Preparation works for structural steel installation
Groundworks and Extension Areas

Roof and External Structure Taking Shape
Visitors nearby will now start to notice major external changes:
• Roof insulation and panel installation underway
• External cladding preparation progressing
• Structural elements being fabricated and installed
Roof installation footage

Inside the Building
Internal works are progressing at pace:
• First-fix partitions being installed
• Ventilation and pipework upgrades ongoing
• Mechanical and electrical systems being prepared
Internal Fit-Out Works

What Happens Next? (Next 4 Weeks)
Over the coming weeks, the site will continue to evolve rapidly. Key activities include:
• Continued roof construction and completion of structural elements
• Installation of steel framework and cladding
• Progress on internal mechanical and electrical systems
• Further development of extension areas
• Installation of internal partitions and space layouts
Thank You
We would like to thank residents, customers and stakeholders for their continued patience and support while these works are ongoing.
This investment will deliver a modern, high-quality leisure facility for the Troon community, and we look forward to sharing further updates as the project progresses.