Works continue at Troon Leisure Club, with the full frame now being erected and showcasing the full new size of the facility. Here are a few updated on what the construction team have been up to over the past few months.  

  • Major refurbishment and extension works continue to progress well at Troon Leisure Centre. 
  • New internal walls and room layouts are now taking shape, with partition works progressing throughout the building. 
  • The first phase of floor screeding has now been completed within the changing village areas. 
  • Mechanical and electrical services continue to be installed throughout the facility, providing the infrastructure required for the new customer spaces. 
  • Significant progress has been made on the new extension, with structural steelwork installed and roof construction advancing. 
  • External wall systems, insulation and fire protection measures are now being installed, helping to define the final appearance of the new facility. 
  • New entrance features, glazing systems and customer-facing facilities are progressing through manufacture ahead of installation later this year. 

Milestone timeline

July 2026
  • Internal partitions and room layouts continuing to be formed. 
  • Mechanical and electrical installation progressing. 
  • Roof construction continuing on extension areas. 
  • Wall cladding and external envelope works progressing.
  • Structural works to new studio and extension elements nearing completion. 
August 2026
  • Internal tiling works commencing within changing areas. 
  • Completion of major roof and external cladding phases. 
  • Installation of curtain walling and glazing elements. 
  • Further progress to external building appearance as scaffolding begins to come down in key areas. 
September 2026
  • Main entrance glazing and screen installations.
  • Internal wall and floor finishes advancing throughout the building.
  • Continued roof completion works on new extensions. 
  • External landscaping and car park infrastructure works beginning in selected areas.
Autumn 2026
  • Wall and floor tiling progressing across refurbished areas. 
  • Decoration and interior finishes commencing. 
  • Installation of specialist building equipment and air handling systems.
  • Solar photovoltaic panels scheduled for installation during November.