Troon Progress Update July 2026
Works continue at Troon Leisure Club, with the full frame now being erected and showcasing the full new size of the facility. Here are a few updated on what the construction team have been up to over the past few months.
-
Major refurbishment and extension works continue to progress well at Troon Leisure Centre.
-
New internal walls and room layouts are now taking shape, with partition works progressing throughout the building.
-
The first phase of floor screeding has now been completed within the changing village areas.
-
Mechanical and electrical services continue to be installed throughout the facility, providing the infrastructure required for the new customer spaces.
-
Significant progress has been made on the new extension, with structural steelwork installed and roof construction advancing.
-
External wall systems, insulation and fire protection measures are now being installed, helping to define the final appearance of the new facility.
-
New entrance features, glazing systems and customer-facing facilities are progressing through manufacture ahead of installation later this year.
Milestone timeline
July 2026
-
Internal partitions and room layouts continuing to be formed.
-
Mechanical and electrical installation progressing.
-
Roof construction continuing on extension areas.
-
Wall cladding and external envelope works progressing.
-
Structural works to new studio and extension elements nearing completion.
August 2026
-
Internal tiling works commencing within changing areas.
-
Completion of major roof and external cladding phases.
-
Installation of curtain walling and glazing elements.
-
Further progress to external building appearance as scaffolding begins to come down in key areas.
September 2026
-
Main entrance glazing and screen installations.
-
Internal wall and floor finishes advancing throughout the building.
-
Continued roof completion works on new extensions.
-
External landscaping and car park infrastructure works beginning in selected areas.
Autumn 2026
-
Wall and floor tiling progressing across refurbished areas.
-
Decoration and interior finishes commencing.
-
Installation of specialist building equipment and air handling systems.
-
Solar photovoltaic panels scheduled for installation during November.